| 23.01.04 |
Commence of Unit 1 containment pneumatic tests.
|
| 22.01.04 |
All activities required at this stage for SDGS diesels NN. 1-4 are finalized.
|
| 20.01.04 |
All 4 circulation pumps are tested supplying water to the turbine condenser. The turbine condenser is filled.
|
| 19.01.04 |
-First inspection of the equipment is finalized.
- Pre-operation inspection of the equipment metal is finalized
- Installation of quick-removing thermal insulation is completed.
- CPS drives are installed.
- Installation and pneumatic tests of the transport lock are completed.
|
| 29.12.03 |
Oil circulation through the turbine oil supply system is going on.
|