| 22.01.04 |
Reactor building – 20 PCP joints out of 36 are welded.
|
| 16.01.04 |
Unit 2 Turbine building - Generator pressure tests and turbine rotor laying for centering are performed
|
| January 2004 |
Installation of Unit 2 firefighting pump house is over and individual tests are started.
|
| January 2004 |
Installation of Unit 2 water treatment plant is over and individual tests are started.
|
|
|
|